Arizona Subcontractor Compliance

Last researched: October 22, 2026

Starting out as a subcontractor in Arizona, or taking your first job there? These are the rules to know. Licensing: State license: Arizona Registrar of Contractors (ROC). Lien deadline: 120 days after completion; 60 days after recorded Notice of Completion. Private-work retainage: No fixed cap; reasonable retention only. Workers' compensation: 1+ employees. Of the 8 subjects below, 0 come from official sources and 8 from secondary sources.

This information is operational guidance, not legal advice. Statutes change and have exceptions. Confirm deadlines with the state agency or an attorney before relying on them for a specific project.

Arizona license Secondary source, verify before relying

State license: Arizona Registrar of Contractors (ROC)

Specialty/trade classifications licensed by ROC, incl. subcontractors. Requirement taken from a secondary guide; confirm with ROC. Local business licenses may also apply.

Source: https://constructionbids.ai/blog/contractor-licensing-requirements-by-state-guide

Get a compliance audit for your company →

Arizona license threshold Secondary source, verify before relying

$1,000 incl. labor and materials; under $1,000 with no permit exempt

Secondary summary. Confirm against A.R.S. 32-1121 before relying.

Source: https://constructionbids.ai/blog/contractor-licensing-requirements-by-state-guide

Get a compliance audit for your company →

Arizona preliminary notice Secondary source, verify before relying

Required: 20-day preliminary notice within 20 days of first furnishing

A.R.S. 33-992.01. Late notice protects only work after service; no notice means no lien rights. Applies to private and public.

Source: https://www.siteline.com/mechanics-lien-rights/arizona

Get a compliance audit for your company →

Arizona lien deadline Secondary source, verify before relying

120 days after completion; 60 days after recorded Notice of Completion

Completion: earlier of 30 days after final inspection/acceptance or 60 days after labor stops (if permit). Foreclose within 6 months of recording.

Source: https://www.siteline.com/mechanics-lien-rights/arizona

Get a compliance audit for your company →

Arizona prompt pay Secondary source, verify before relying

7 days after GC receives owner payment; 1.5%/month interest plus fees

A.R.S. Title 32 Ch. 10 Art. 5 (32-1181 to 1188), esp. 32-1183. Prevailing party recovers attorney fees. GC needs 7-day written notice before stopping work.

Source: https://www.siteline.com/prompt-payment-laws/arizona

Get a compliance audit for your company →

Arizona retainage (private work) Secondary source, verify before relying

No fixed cap; reasonable retention only

A.R.S. 32-1182(D),(E): owner may withhold reasonable retention limited to expected direct costs.

Source: https://www.levelset.com/retainage/arizona-retainage-faqs/

Get a compliance audit for your company →

Arizona retainage (public work) Secondary source, verify before relying

10%, reduced to 5% after 50% complete if progress satisfactory

A.R.S. 34-221(C). Half of retention releasable at 50% on request; balance within 60 days of completion.

Source: https://www.levelset.com/retainage/arizona-retainage-faqs/

Get a compliance audit for your company →

Arizona workers' compensation Secondary source, verify before relying

1+ employees

No special construction rule listed in the source. Source is an AI-generated summary (workerscompensation.com); confirm with the state workers' compensation agency.

Source: https://www.workerscompensation.com/state-contact-info/workers-compensation-law-all-50-states-basics-powered-by-ai/