Rhode Island Subcontractor Compliance
Starting out as a subcontractor in Rhode Island, or taking your first job there? These are the rules to know. Licensing: Yes: CRLB registration for contractors and subs; trades (electrical, plumbing, mechanical) licensed by DLT. Lien deadline: Record Notice of Intention within 200 days after furnishing. Private-work retainage: 5% max of any progress payment. Workers' compensation: 1+ employees. Of the 8 subjects below, 2 come from official sources and 6 from secondary sources.
This information is operational guidance, not legal advice. Statutes change and have exceptions. Confirm deadlines with the state agency or an attorney before relying on them for a specific project.
Rhode Island license Official source
Yes: CRLB registration for contractors and subs; trades (electrical, plumbing, mechanical) licensed by DLT
R.I. Gen. Laws 5-65-3(a),(i): non-employee subs must register before work; GC may not hire unregistered sub. Unregistered contractors lose lien rights (per Levelset).
Source: https://webserver.rilegislature.gov/Statutes/TITLE5/5-65/5-65-3.htm
Get a compliance audit for your company →Rhode Island license threshold Official source
No state threshold for registration
5-65-3 sets no dollar threshold; $1,000 figure applies only to written-contract requirement (5-65-3(o)). Exemptions in 5-65-2 not yet reviewed.
Source: https://webserver.rilegislature.gov/Statutes/TITLE5/5-65/5-65-3.htm
Get a compliance audit for your company →Rhode Island preliminary notice Secondary source, verify before relying
Not required for subcontractors
Only parties contracting directly with owner send Notice of Possible Mechanic's Lien. R.I. Gen. Laws 34-28.
Source: https://www.siteline.com/mechanics-lien-rights/rhode-island
Get a compliance audit for your company →Rhode Island lien deadline Secondary source, verify before relying
Record Notice of Intention within 200 days after furnishing
Mail by certified mail and record; file suit and lis pendens within 40 days of recording. R.I. Gen. Laws 34-28-4, 34-28-10.
Source: https://www.siteline.com/mechanics-lien-rights/rhode-island
Get a compliance audit for your company →Rhode Island prompt pay Secondary source, verify before relying
Pay subs within 7 days after receiving payment
Levelset FAQ states 7 days per tier but cites no statute; private retainage statute 37-12-10.1(e) allows 30 days plus 7 per tier. Verify.
Source: https://www.levelset.com/retainage/rhode-island-retainage-faqs/
Get a compliance audit for your company →Rhode Island retainage (private work) Secondary source, verify before relying
5% max of any progress payment
R.I. Gen. Laws 37-12-10.1(a); applies to contracts defined in 5-65-1 (excludes 1-4 dwelling units). Late retainage interest 10%/yr per Levelset.
Source: https://www.levelset.com/retainage/rhode-island-retainage-faqs/
Get a compliance audit for your company →Rhode Island retainage (public work) Secondary source, verify before relying
5% max of contract price or payment
R.I. Gen. Laws 37-12-10 unless parties agree otherwise; RIDOT has own 5% provision.
Source: https://www.levelset.com/retainage/rhode-island-retainage-faqs/
Get a compliance audit for your company →Rhode Island workers' compensation Secondary source, verify before relying
1+ employees
No special construction rule listed in source. Verify with RI Department of Labor and Training. Source is an AI-generated summary (workerscompensation.com).
Get a compliance audit for your company →More compliance information