Rhode Island Subcontractor Compliance

Last researched: October 22, 2026

Starting out as a subcontractor in Rhode Island, or taking your first job there? These are the rules to know. Licensing: Yes: CRLB registration for contractors and subs; trades (electrical, plumbing, mechanical) licensed by DLT. Lien deadline: Record Notice of Intention within 200 days after furnishing. Private-work retainage: 5% max of any progress payment. Workers' compensation: 1+ employees. Of the 8 subjects below, 2 come from official sources and 6 from secondary sources.

This information is operational guidance, not legal advice. Statutes change and have exceptions. Confirm deadlines with the state agency or an attorney before relying on them for a specific project.

Rhode Island license Official source

Yes: CRLB registration for contractors and subs; trades (electrical, plumbing, mechanical) licensed by DLT

R.I. Gen. Laws 5-65-3(a),(i): non-employee subs must register before work; GC may not hire unregistered sub. Unregistered contractors lose lien rights (per Levelset).

Source: https://webserver.rilegislature.gov/Statutes/TITLE5/5-65/5-65-3.htm

Get a compliance audit for your company →

Rhode Island license threshold Official source

No state threshold for registration

5-65-3 sets no dollar threshold; $1,000 figure applies only to written-contract requirement (5-65-3(o)). Exemptions in 5-65-2 not yet reviewed.

Source: https://webserver.rilegislature.gov/Statutes/TITLE5/5-65/5-65-3.htm

Get a compliance audit for your company →

Rhode Island preliminary notice Secondary source, verify before relying

Not required for subcontractors

Only parties contracting directly with owner send Notice of Possible Mechanic's Lien. R.I. Gen. Laws 34-28.

Source: https://www.siteline.com/mechanics-lien-rights/rhode-island

Get a compliance audit for your company →

Rhode Island lien deadline Secondary source, verify before relying

Record Notice of Intention within 200 days after furnishing

Mail by certified mail and record; file suit and lis pendens within 40 days of recording. R.I. Gen. Laws 34-28-4, 34-28-10.

Source: https://www.siteline.com/mechanics-lien-rights/rhode-island

Get a compliance audit for your company →

Rhode Island prompt pay Secondary source, verify before relying

Pay subs within 7 days after receiving payment

Levelset FAQ states 7 days per tier but cites no statute; private retainage statute 37-12-10.1(e) allows 30 days plus 7 per tier. Verify.

Source: https://www.levelset.com/retainage/rhode-island-retainage-faqs/

Get a compliance audit for your company →

Rhode Island retainage (private work) Secondary source, verify before relying

5% max of any progress payment

R.I. Gen. Laws 37-12-10.1(a); applies to contracts defined in 5-65-1 (excludes 1-4 dwelling units). Late retainage interest 10%/yr per Levelset.

Source: https://www.levelset.com/retainage/rhode-island-retainage-faqs/

Get a compliance audit for your company →

Rhode Island retainage (public work) Secondary source, verify before relying

5% max of contract price or payment

R.I. Gen. Laws 37-12-10 unless parties agree otherwise; RIDOT has own 5% provision.

Source: https://www.levelset.com/retainage/rhode-island-retainage-faqs/

Get a compliance audit for your company →

Rhode Island workers' compensation Secondary source, verify before relying

1+ employees

No special construction rule listed in source. Verify with RI Department of Labor and Training. Source is an AI-generated summary (workerscompensation.com).

Source: https://www.workerscompensation.com/state-contact-info/workers-compensation-law-all-50-states-basics-powered-by-ai/