Starting out as a subcontractor in South Dakota, or taking your first job there? These are the rules to know. Licensing: No state GC/specialty license; only electrical and plumbing are state licensed. Lien deadline: 120 days after last furnishing of labor or materials (SDCL 44-9-15). Private-work retainage: No statutory cap. Workers' compensation: Not statutorily mandatory per SD DLR; coverage effectively elective. Of the 8 subjects below, 1 comes from official sources and 7 from secondary sources.

This information is operational guidance, not legal advice. Statutes change and have exceptions. Confirm deadlines with the state agency or an attorney before relying on them for a specific project.

South Dakota license Secondary source, verify before relying

No state GC/specialty license; only electrical and plumbing are state licensed

Electrical and Plumbing Commissions under Dept. of Labor & Regulation. Contractor's excise tax license (Dept. of Revenue) is tax registration only. HVAC and general contractor licensing is local only (Sioux Falls, Rapid City).

Source: https://www.harborcompliance.com/south-dakota-construction-license

Get a compliance audit for your company →

South Dakota license threshold Secondary source, verify before relying

No state threshold

No project-value trigger found for state electrical/plumbing licenses; local jurisdictions set their own rules.

Source: https://www.procore.com/library/south-dakota-contractors-license

Get a compliance audit for your company →

South Dakota preliminary notice Secondary source, verify before relying

Not required of subs; only sub-subs/suppliers, and only if owner posts commencement notice

SDCL 44-9-53: second-tier subs and suppliers send notice within 60 days of last furnishing if a Notice of Project Commencement was filed and posted (44-9-50). Levelset FAQ is internally inconsistent; confirm.

Source: https://www.levelset.com/mechanics-lien/south-dakota-lien-law-faqs/

Get a compliance audit for your company →

South Dakota lien deadline Secondary source, verify before relying

120 days after last furnishing of labor or materials (SDCL 44-9-15)

Unclear if counted from claimant's own last work or the project's; count from own last work. Enforcement suit within 6 years (44-9-24). Private projects only.

Source: https://www.siteline.com/mechanics-lien-rights/south-dakota

Get a compliance audit for your company →

South Dakota prompt pay Secondary source, verify before relying

No private-project prompt payment statute; contract governs

SDCL 5-26-1 to 5-26-8 cover public projects only. No statutory interest on private GC-to-sub payments.

Source: https://www.levelset.com/prompt-payment/south-dakota-prompt-payment-faqs/

Get a compliance audit for your company →

South Dakota retainage (private work) Secondary source, verify before relying

No statutory cap

South Dakota has no retainage statute for private projects; amount and release set by contract.

Source: https://www.levelset.com/retainage/south-dakota-retainage-faqs/

Get a compliance audit for your company →

South Dakota retainage (public work) Secondary source, verify before relying

County building contracts: 12% first $50K, 5% next $200K, 2.5% above

SDCL 7-25-10 sets these as minimum retention percentages for county projects per Levelset. State-agency project retainage rule not verified.

Source: https://www.levelset.com/retainage/south-dakota-retainage-faqs/

Get a compliance audit for your company →

South Dakota workers' compensation Official source

Not statutorily mandatory per SD DLR; coverage effectively elective

DLR page says no law requires employers to carry coverage; uninsured employers can be sued in civil court. GC liable for sub employees under SDCL 62-3-10 (Alfa, secondary). Secondary sources claim 1+ employees; conflict flagged.

Source: https://dlr.sd.gov/workers_compensation/