Utah Subcontractor Compliance
Starting out as a subcontractor in Utah, or taking your first job there? These are the rules to know. Licensing: Yes: Utah DOPL contractor license by classification (general/specialty). Lien deadline: 180 days after final completion; 90 days after Notice of Completion if filed. Private-work retainage: 5% max of each payment and of total construction price. Workers' compensation: All employers with employees must cover them (1+); few exceptions. Of the 8 subjects below, 1 comes from official sources and 7 from secondary sources.
This information is operational guidance, not legal advice. Statutes change and have exceptions. Confirm deadlines with the state agency or an attorney before relying on them for a specific project.
Utah license Secondary source, verify before relying
Yes: Utah DOPL contractor license by classification (general/specialty)
Qualifier, insurance, and workers comp (if employees) required. Electrical licensed by DOPL; no state plumbing contractor license (individual plumber licenses). Fire sprinkler: Harbor says State Fire Marshal; Utah Code 58-55-305 references DOPL fire suppression license; verify.
Source: https://www.harborcompliance.com/utah-construction-license
Get a compliance audit for your company →Utah license threshold Secondary source, verify before relying
Exempt under $7,000 (labor+materials); insurance affirmation above $3,000
Utah Code 58-55-305(1)(h) per Justia copy (may not be latest). Electrical, plumbing, HVAC, and fire-protection systems work still needs licensed contractors even under $7,000.
Source: https://law.justia.com/codes/utah/title-58/chapter-55/part-3/section-305/
Get a compliance audit for your company →Utah preliminary notice Secondary source, verify before relying
Preliminary notice to State Construction Registry within 20 days of starting work
Utah Code 38-1a-501. Late notice protects only work from 5 days before filing onward. Cannot be filed more than 10 days after a Notice of Completion.
Source: https://www.siteline.com/mechanics-lien-rights/utah
Get a compliance audit for your company →Utah lien deadline Secondary source, verify before relying
180 days after final completion; 90 days after Notice of Completion if filed
Utah Code 38-1a-502, 38-1a-507. Owner may file NOC without notifying subs, so monitor registry. Send lien copy to owner within 30 days; foreclose within 180 days of recording.
Source: https://www.siteline.com/mechanics-lien-rights/utah
Get a compliance audit for your company →Utah prompt pay Secondary source, verify before relying
30 days after GC receives owner payment; retainage within 10 days; 1%/month interest
Utah Code 58-55-603 (progress payments, interest plus collection costs and fees); 13-8-5(9): retention passed down within 10 days; 2%/month charge for knowing wrongful retention withholding.
Source: https://www.levelset.com/prompt-payment/utah-prompt-payment-faqs/
Get a compliance audit for your company →Utah retainage (private work) Secondary source, verify before relying
5% max of each payment and of total construction price
Utah Code 13-8-5(3). Levelset notes the statute is unclear on several issues.
Source: https://www.levelset.com/retainage/utah-retainage-faqs/
Get a compliance audit for your company →Utah retainage (public work) Secondary source, verify before relying
5% max of total construction price
Utah Code 13-8-5(3)(b); retainage held by others cannot exceed the amount the public entity retained.
Source: https://www.levelset.com/retainage/utah-retainage-faqs/
Get a compliance audit for your company →Utah workers' compensation Official source
All employers with employees must cover them (1+); few exceptions
Labor Commission: every employer must cover all employees (Utah Code 34A-2-201 exceptions). 1+ reading of 34A-2-103 is from a study guide. GC is statutory employer of uninsured subs' employees.
Source: https://laborcommission.utah.gov/?p=3047